The power industry specialists intend to complete reconstruction by the end of 2012. Vologdaenergo branch of IDGC of the North-West, JSC is implementing a socially significant investment project for reconstruction of “Roslyatino” 110/10 kV substation in the Babushkinsky District, Vologda Region. The project CAPEX will make 169.4 mln RUR. The activities currently completed at the power industry facility by efforts of the contractor organization include the territory partial filling and the grounding device assembly; in progress are works for an oil sump system arrangement, a 110 kV voltage class pole having been installed. Reconstruction of “Roslyatino” 110/10 kV substation will result in replacement of the equipment of the 110 kV outdoor switchgear, 110/10 kV power transformers (with two 2.5 MVA transformers) as well as 110 kV voltage and current transformers (with gas-insulated ones). Additionally, the substation will undergo replacement of relay protection and telemechanics system equipment. The project implementation will enable reduction of losses within the Company’s grids, decrease of expenditures on repair and emergency recovery works as well as improvement of reliability and quality of electric power supply to consumers in the Babushkinsky District. The power industry specialists intend to complete reconstruction by the end of 2012.
|