print version 

Find company
Home About the ProjectContact usFor the Clients
Enter code or ISIN
 
alpha / industry search

Issuers' Corner
Press Releases
Annual Reports Library

Financial Statements
SEC & FFMS Filings
Corporate Presentations
GM Materials
Issues Documents
Corporate Governance Materials
Russian Company Guide
Company Profiles
Corporate Calendar
Markets Corner
Consensus Estimates
Media Corner
News Line


Get updates



Home  Issuers' Corner  Press Releases REGISTER LOG IN

Press Releases

company search
all press releases
all Unified Energy System press releases

Unified Energy System

December 9, 2004

RAO "UES of Russia" announces results of the open tender to select General Contractor to modernize Ivanovskaya TPP

Moscow, 9 December 2004. As a result of the open tender to select General Contractor to modernize Ivanovskaya TPP, RAO "UES of Russia" awarded the contract to FGUP "VO "Technopromexport".

The project to modernize and expand Ivanovskaya TPP envisages installation of two combined-cycle generating units PGU-325 MW using the gas turbine generators GTE-110. Under the terms of the tender, Technopromexport will handle the installation of the first start-up complex PGU-325 and the overall equipment supply.

Power installations of this kind increase efficiency of power generation units from 35-38% to 51% and help reduce consumption of fuel (natural gas) by 30% at each upgraded power generation units. The installation of the combined-cycle generating units at Ivanovskaya TPP is in line with the RAO UES strategy designed to reequip its enterprises using advanced technologies.

In accordance with the schedule for construction of PGU-325 MW at Ivanovskaya TPP, in 2005 it is planned to complete the construction of all principal and auxiliary buildings and structures and start installation of primary equipment. The installation of the first start-up complex of PGU-325 is scheduled for completion in 2007.

The modernization and expansion project at Ivanovskaya TPP will be carried out as part of the Investment Programme 2005 of RAO "UES of Russia". Under the Programme, RUB3.8 billion in earmarked investment allocations and borrowed funds will be used to finance the project.

_______________________________________________________________________________

Construction of new power plants and re-equipment and modernization of the existing power plants using combined-cycle technologies is a top priority in the investment policy of RAO "UES of Russia".

To date, RAO "UES of Russia" has put into operation the first generation unit of 450 MW at Severo-Zapadnaya CHPP in Leningrad Region and a 220-MW generation unit at Tyumenskaya CHPP-1, both of which use combined cycle technology.

On 20 December 2004, RAO "UES of Russia" plans to commission the Sochinskaya combined-cycle power plant (78 MW) in Krasnodar Kray. A project is underway to build Kaliningradskaya CHPP. The plant's first 450-MW generating unit is scheduled for commissioning in November 2005.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z


Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer