print version 

Find company
Home About the ProjectContact usFor the Clients
Enter code or ISIN
 
alpha / industry search

Issuers' Corner
Press Releases
Annual Reports Library

Financial Statements
SEC & FFMS Filings
Corporate Presentations
GM Materials
Issues Documents
Corporate Governance Materials
Russian Company Guide
Company Profiles
Corporate Calendar
Markets Corner
Consensus Estimates
Media Corner
News Line


Get updates



Home  Issuers' Corner  Press Releases REGISTER LOG IN

Press Releases

company search
all press releases
all Rosseti Volga press releases

Rosseti Volga

February 13, 2009

In Penza a new substation is put into operation by “Penzaenergo” branch of “Interregional Distribution Grid Company of Volga”, JSC

"Penzaenergo" has put into operation new socially significant object - substation "Izumrudnaya". Such scale building of electrical-power objects was not implemented in the city of Penza for 20 years. The sum of investments for building of substation "Izumrudnaya" has made 133 million roubles. The necessity for building of new substation is caused by dynamical rates of development of area Arbekovo. Existing substations are overloaded and cannot supply new consumers with the electric power. The first objects are already connected to substation "Izumrudnaya".

Commissioning of new substation gives the chance to unload operating substation "Arbekovo" that will raise reliability of power supply of the area. «This year we have ordered two more projects of substations, - Sergey Esjakov, the director of “Penzaenergo” branch of “Interregional Distribution Grid Company of Volga”, JSC  has told. – One of them, "Arbekovo-3", will be situated behind a traffic police post at departure from Arbekovo on a route Moscow-Samara. Its purpose – connection of new consumers. Now in the given point active building of large objects is conducted The electric power is necessary for these objects. The second project is connected with the governor's program on building of the cement works one of which will be situated  in Nikolsky region. In this direction the electric main is under construction and in this connection our substation »will be reconstructed now.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z


Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer